Client: Cannock Chase DC Location: Cannock, Staffordshire Value: £4.7 million

Design & Build

This Design & Build project involved the complete refurbishment and modernisation of Chase Leisure Centre in Cannock.

Works included new doors, ceiling, windows and floor finishes, to bring them up to Fire, Building and Sport England regulations. The building was re-roofed with a curved roof covering the swimming pool area. The external facades were re-cladded with insulated render.

The project was carried out in 3 phases to allow for the leisure centre to remain open throughout the refurbishment programme.

Contract Period: 60 weeks

The facility now homes a new main entrance and café area, offices and back of house facilities. Main corridors were converted into a new gymnasium.

The pool area was extended and a new wet changing facility created. A moveable floor was constructed in to the pool allowing a multitude of activities. The pools filtration equipment was completely upgraded. Refurbishment to the golfing area was carried out and a new golf changing area, reception and lounge created.

 

 

WE BUILD ON OUR EXPERIENCE

Site Map Accessibilty Privacy Policy Equality and Diversity Policy
Anti Modern Slavery Statement Covid Procedures Carbon Reduction Plan Join Our Mailing List Find Us

Copyright © G F Tomlinson Group Ltd 2026